NuclearVox

Edition 3 — Week of November 23, 2026

Seven stories this week: Darlington's cost fight moves to the Ontario Energy Board, Canadian reactor technology gets a study contract in Türkiye, fuel deals land for two advanced reactor designs, and a Swedish lead-cooled reactor signs the first HALEU contract of its kind. This edition's permanent page →

The Ontario Energy Board has ordered the parties in OPG's Darlington rate case back into settlement talks, directing them to resume discussions on December 8 and report by December 11 on whether a settlement is reachable. The order follows OPG's November 10 disclosure, covered in Edition 2, that Unit 1 will miss its October 2030 target and its C$7.7 billion estimate; OPG's filing also pulled the project's forecast generation out of its 2027 to 2031 rate application entirely, while construction on the reactor and turbine buildings continues.

Why it matters: this is where the overrun stops being a press release and becomes a bill. What the settlement produces decides how much of Darlington's new cost lands in Ontario electricity rates, and it is the first hard test of the case for building Units 2 to 4 on the original numbers.

Engineering News-Record · November 17, 2026 · Read the original → · Background: ReNew Canada's summary of OPG's third quarter disclosure, November 12, 2026

AtkinsRéalis subsidiary Candu Energy has signed a memorandum of agreement with Türkiye's state nuclear company TÜNAŞ to deliver a feasibility study and front-end engineering design for a possible multi-unit CANDU plant, with a six-unit, roughly 4.5 GW station under discussion and first power talked about for 2036. The agreement, signed at the COP31 summit in Antalya, covers study work only: no site is confirmed, no construction contract exists, and the study is expected to run to the end of 2027.

Why it matters: it is the most concrete export opening for Canadian reactor technology in years, and it puts the Darlington supply chain's home team in line for a second major programme if Türkiye chooses CANDU for its second or third plant.

AtkinsRéalis · November 12, 2026 · Read the original → · Also reported by World Nuclear News, November 12, 2026

Swedish developer Blykalla and enricher Urenco have signed an agreement under which uranium feed supplied by Blykalla will be enriched into HALEU at Urenco's Capenhurst plant in the UK to fuel Blykalla's first SEALER unit in the United States, with deliveries expected to begin in the early 2030s. The 55 MWe lead-cooled SEALER is designed to be factory built and road transportable, and Blykalla is planning a phased US demonstration called Fjäll, targeting a zero-power reactor in 2027 before a power-producing unit.

Why it matters: HALEU supply is the bottleneck under almost every advanced reactor schedule, and this is the first commercial enrichment contract written for a lead-cooled design. It is also a European enricher signing up to fuel a first unit being built in the US.

World Nuclear News · November 17, 2026 · Read the original →

ARC Clean Technology has announced a memorandum of understanding with South Korea's POSCO International to explore an integrated fuel supply chain for the ARC-100, covering raw material supply, enrichment, deconversion and fuel fabrication for the reactor's HALEU-based uranium-zirconium metal fuel, with POSCO International in line as a potential fuel supplier to ARC projects. The MOU was signed on September 22, 2026 and announced November 17. ARC, a US DOE demonstration programme awardee tracked in the NuclearVox directory, is advancing its first US deployment at Idaho National Laboratory, with programmes also running in Canada and Türkiye.

Why it matters: ARC is attacking the same fuel problem as the Urenco deal from the other end, assembling the full chain before it has a plant to fuel. Whether these paper supply chains close is what decides if the ARC-100's schedule means anything.

ARC Clean Technology · November 17, 2026 · Read the original →

Terra Innovatum reported on November 16 that it has delivered all 18 chapters of the draft preliminary safety analysis report for its SOLO micro-modular reactor to the US Nuclear Regulatory Commission for a readiness review, ahead of a planned construction permit application. The company, which ended September with US$82.4 million in cash, also signed a non-binding letter of intent covering up to 8 MWe of behind-the-meter SOLO capacity for data centre infrastructure in Argentina and Brazil, and still targets a first deployment in 2027, subject to regulatory approvals.

Why it matters: a complete draft safety report is the moment a microreactor concept becomes a licensing project. SOLO is a 1 MWe class design aiming to deploy years before the big SMRs, and its NRC reception will be an early read on how the agency handles very small reactors.

Terra Innovatum · November 16, 2026 · Read the original →

Elementl Power, one of the ten developers New York qualified in Edition 2's NYPA story and the developer behind Google's three advanced nuclear projects announced in 2025, said on November 17 that Google Cloud will help it build AI tools for the preconstruction stage of nuclear projects. The first tool, Atlas, screens potential sites across reactor designs, and Elementl says early analysis that took months can now be done in days or weeks, though that saving covers early screening only, not licensing or construction.

Why it matters: preconstruction is where nuclear schedules quietly die, in siting, technology selection and regulatory preparation. A developer with Google's backing industrialising that stage is worth watching, with the caveat that faster screening is not faster building.

Unite.AI · November 17, 2026 · Read the original →

Bangladesh's Rooppur Unit 1 supplied electricity to the national grid for the first time on November 17, delivering about 350 MW in a trial run and making Bangladesh the 33rd country to generate nuclear electricity. The Russian-built VVER-1200 is the first of two 1,200 MW units; a roughly ten-month trial period runs before commercial operation at full capacity, and the project deadline now sits at June 2028.

Why it matters: a framing note for readers rather than an SMR story. Rooppur is a large reactor, not an SMR, and its path from first criticality in October to first power in November is the commissioning rhythm every SMR project on this site still has ahead of it.

Asia Daily · November 17, 2026 · Read the original →

Edition 2 — Week of November 16, 2026

Six stories this week: Ontario's flagship build slips on cost and schedule while its supply chain expands in Cambridge, the US issues a landmark construction permit for an SMR-powered industrial site in Texas, Oklo secures its fuel, New York lines up its nuclear developers, and a Wisconsin co-op looks at SMRs for a former nuclear site. This edition's permanent page →

OPG says the first BWRX-300 at Darlington is no longer expected to start commercial operation by October 2030 or to be built within its $7.7 billion estimate, which includes systems shared by all four planned units. The company blames the knock-on effects of GE Vernova Hitachi's ongoing first-of-a-kind engineering on construction and supply chain work, and says a full cost and schedule reassessment should be substantially complete by mid-2027, with no new date or cost given yet.

Illustration of how the completed BWRX-300 at Darlington could look
An illustration of how the completed BWRX-300 at Darlington could look. Image: Ontario Power Generation (OPG)
Ontario Power Generation · November 10, 2026 · Read the original → · Also reported by World Nuclear News, November 11, 2026

BWX Technologies has completed the roughly C$80 million expansion of its Cambridge, Ontario plant, adding 55,000 square feet and enlarging its commercial nuclear clean room by 40%. The plant is fabricating the reactor pressure vessel for the Darlington SMR alongside 48 steam generators for Pickering's refurbishment, and the expansion has created 200 long-term jobs, with 200 more hires targeted over the next year.

BWXT's expanded Cambridge manufacturing facility, seen from above
Image: BWX Technologies (BWXT)
BWX Technologies · November 12, 2026 · Read the original → · Also reported by World Nuclear News

The US Nuclear Regulatory Commission has issued the construction permit for Long Mott Generating Station, the four-unit Xe-100 plant proposed for Dow's Seadrift site in Texas — the first NRC construction permit for a high-temperature gas-cooled reactor in nearly 60 years, and the first for a nuclear plant at an industrial site. The permit lets the project be built but not operated, and Dow still has to make its own investment decisions, with a preliminary decision expected in 2027, before full-scale construction begins. This follows the final safety review covered in Edition 1.

Aerial rendering of the Long Mott Generating Station, the four-unit Xe-100 plant planned for Dow's Seadrift site in Texas
A rendering of the Long Mott Generating Station. Image: X-energy
World Nuclear News · November 10, 2026 · Read the original → · X-energy's announcement, November 9, 2026

Oklo has turned its June letter of intent with Centrus Energy into definitive multi-year contracts for high-assay low-enriched uranium, enough to fuel up to five Aurora powerhouses for multiple years, with deliveries from Centrus' Piketon, Ohio plant scheduled to begin in 2029. Oklo's prepayments, backed by Meta's prepayment for future power, will help Centrus build new US enrichment capacity, and the fuel covers the first phase of Oklo's planned 1.2 GW Ohio campus.

Centrus' American Centrifuge Plant in Piketon, Ohio, seen from above
Centrus' American Centrifuge Plant in Piketon, Ohio. Image: Centrus Energy
Centrus Energy / Oklo · November 12, 2026 · Read the original →

The New York Power Authority has qualified 10 developers for potential partnership on at least 1 GW of advanced nuclear capacity in upstate New York. Six firms qualified for both large reactors and SMRs, while four advanced on the SMR path only: Blue Energy, Holtec International, TerraPower and X-energy — three of them companies tracked in the NuclearVox directory. A host community, technology and development partner are still to be chosen.

New York Power Authority · November 12, 2026 · Read the original →
Top-down rendering of Applied Atomics' SMR site design Image: Applied Atomics Inc.
Industry

Wisconsin co-op Dairyland to study SMRs at its Genoa site

Wisconsin's Dairyland Power Cooperative has signed a letter of intent with Applied Atomics to evaluate deploying that company's 100–150 MW SMRs at Dairyland's Genoa site, a former nuclear plant site that still holds a licensed spent fuel store, with a possible power purchase agreement to follow. A feasibility study comes first, and Dairyland says it expects to be able to decide on a binding PPA in roughly nine months, only if the numbers work for its members.

Top-down rendering of Applied Atomics' small modular reactor design
A rendering of Applied Atomics' SMR technology. Image: Applied Atomics Inc.
America's Electric Cooperatives (NRECA) · November 13, 2026 · Read the original →

Edition 1 — Week of November 9, 2026

Four stories this week: Ontario puts local factories to work on the Darlington build, a US regulator finishes its safety review of the Xe-100, NuScale starts cutting metal, and Europe puts construction money behind a heating reactor. This edition's permanent page →

CNSC inspectors at the Darlington New Nuclear Project site before the reactor basemat lift Image: Canadian Nuclear Safety Commission (CNSC)
Ontario

Ontario awards 14 supply contracts for the Darlington SMR build

The Ontario government has awarded 14 contracts to manufacturers across the Greater Toronto and Hamilton Area to supply the Darlington New Nuclear Project, covering transformers, pumps, specialized steel and concrete for the first BWRX-300. The province says the work adds more than $110 million to Ontario's GDP, and that more than 100 Canadian companies now hold agreements with OPG on the project.

The Darlington reactor basemat being hoisted into the reactor building shaft, April 2026
The basemat for Darlington's first BWRX-300 being hoisted into the reactor building shaft, April 2026. Image: Canadian Nuclear Safety Commission (CNSC)
Canadian Manufacturing · November 6, 2026 · Read the original →

Calogena, a French developer building a 30 MW heat-only reactor for district heating, has been awarded €40 million from the European Commission's Innovation Fund toward its first commercial unit at Pierrelatte in southern France. The company says it is the first time EU funding for an SMR has gone directly toward building a commercial installation; the grant is support toward potential construction, not a construction decision, and Calogena targets deployment from 2030.

Rendering of the Calogena CAL30 reactor core inside its vessel
Image: Calogena
EnergyNews.biz · Announced November 5, 2026 · Read the original →

NuScale Power has signed a manufacturing contract with South Korea's Doosan Enerbility for first-article production of the upper reactor coolant system, the top section of the reactor pressure vessel in its Power Module. The work, at Doosan's Changwon plant, moves the partnership that began in 2019 from design and materials work into physical fabrication of commercial-grade components.

NuScale Power Module, showing the upper reactor coolant system that Doosan will fabricate
Image: NuScale Power
Nuclear Engineering International · November 3, 2026 · Read the original →

The US Nuclear Regulatory Commission has issued its Final Safety Evaluation Report for the Long Mott Generating Station, the four-unit Xe-100 plant Dow plans at its Seadrift site in Texas, to supply power and process steam. With the environmental review completed in May, both primary NRC reviews are done and the Advisory Committee on Reactor Safeguards supports issuing a construction permit; the permit itself is still to come.

Close-up rendering of the Xe-100 reactor vessel
Image: X-energy
EnergyNews · November 2, 2026 (safety report issued October 30, 2026) · Read the original →