Ontario is building the first grid-scale small modular reactor in the G7: a GE Hitachi BWRX-300 at Ontario Power Generation's Darlington New Nuclear Project in Clarington, with three more units planned behind it. This page tracks the build milestone by milestone, each one dated and linked to its source. Follow the week-to-week developments in This Week in SMRs.
After a review process that began in 2018, OPG announces it will partner with GE Hitachi Nuclear Energy on its BWRX-300 reactor for the Darlington new nuclear site, the design around which the whole project is built.

The Ontario government announces it will work with OPG to start planning and licensing for three additional SMRs at Darlington, for a total of four units and 1,200 MW of output, enough for about 1.2 million homes. Units two to four still need their own regulatory approvals before construction.
The Canadian Nuclear Safety Commission authorises OPG to construct one BWRX-300 at Darlington, the first commercial SMR construction licence in North America. The licence runs to March 31, 2035 and carries three regulatory hold points that OPG must clear as construction proceeds.
The province gives OPG the go-ahead to start construction of the first unit. OPG prices the first SMR at $6.1 billion, plus $1.6 billion for systems and services shared across all four units, with a total budget of $20.9 billion for the full four-unit project, costs expected to fall with each unit after the first.
OPG files its application with the CNSC for a 20-year Licence to Operate the first SMR, the approval needed to complete commissioning, load fuel and enter commercial operation once construction is finished. The application is being submitted in packages over several months, ahead of a public hearing.
The CNSC removes Regulatory Hold Point 1 after verifying OPG's commitments, clearing installation of the reactor building foundation. The next hold point covers installation of the reactor pressure vessel, which OPG has already procured.

The basemat module, the foundation of the Unit 1 reactor building, is lifted into the excavated reactor shaft: a ring about 37 metres across weighing close to a thousand tonnes, set more than 30 metres below grade. It is the project's first big physical construction milestone.

OPG's summer 2026 construction update reports the reactor building progressing upward from the basemat, with the first two shaft wall rings installed, major concrete work on the condenser cooling water system, and the tunnel boring machine's main drive installed ahead of tunnelling in the fall.
OPG's third-quarter 2026 update reports two construction steps completed in the quarter: assembly of the tunnel boring machine that will bore and line the condenser cooling water tunnel, with tunnelling expected to begin in the last quarter of 2026, and the first concrete pour for the turbine building foundation.
The province announces 14 contracts for GTHA manufacturers to supply the Darlington build, including transformers, pumps, specialized steel and concrete, work it values at more than $110 million in GDP. More than 100 Canadian companies now hold supply agreements with OPG on the project.
In its third-quarter results, OPG says Unit 1 is no longer expected to achieve its October 2030 commercial operation target or be completed within its $7.7 billion estimate, which includes systems and services common to all four planned units. OPG cites GE Vernova Hitachi's ongoing engineering for the first-of-a-kind design and its effects on construction execution and supply chain performance. A comprehensive cost and schedule assessment is expected to be substantially complete by mid-2027; OPG has given no new date or cost.
OPG's operating licence application ends in a public hearing before the Commission, where members of the public can comment. As of this page's last verification, the CNSC had not set the hearing date.
The second of the construction licence's three regulatory hold points covers installation of the reactor pressure vessel, the heart of the plant. CNSC staff must verify OPG's commitments before that work proceeds.

OPG's planning goal is to finish building the first SMR by the end of the decade and connect it to the grid by the end of 2030, which would make it the first operating grid-scale SMR in the Western world. Units two to four follow on a staged schedule, applying lessons from Unit 1, once their own approvals are in place.
Update, Nov 10, 2026: OPG has said Unit 1 will miss its October 2030 operation target and C$7.7B estimate; a reassessment is due mid-2027. The end-of-2030 date above is OPG's earlier stated goal.