Six stories this week: Ontario's flagship build slips on cost and schedule while its supply chain expands in Cambridge, the US issues a landmark construction permit for an SMR-powered industrial site in Texas, Oklo secures its fuel, New York lines up its nuclear developers, and a Wisconsin co-op looks at SMRs for a former nuclear site.

OPG says the first BWRX-300 at Darlington is no longer expected to start commercial operation by October 2030 or to be built within its $7.7 billion estimate, which includes systems shared by all four planned units. The company blames the knock-on effects of GE Vernova Hitachi's ongoing first-of-a-kind engineering on construction and supply chain work, and says a full cost and schedule reassessment should be substantially complete by mid-2027, with no new date or cost given yet.

Illustration of how the completed BWRX-300 at Darlington could look
An illustration of how the completed BWRX-300 at Darlington could look. Image: Ontario Power Generation (OPG)
Ontario Power Generation · November 10, 2026 · Read the original → · Also reported by World Nuclear News, November 11, 2026

BWX Technologies has completed the roughly C$80 million expansion of its Cambridge, Ontario plant, adding 55,000 square feet and enlarging its commercial nuclear clean room by 40%. The plant is fabricating the reactor pressure vessel for the Darlington SMR alongside 48 steam generators for Pickering's refurbishment, and the expansion has created 200 long-term jobs, with 200 more hires targeted over the next year.

BWXT's expanded Cambridge manufacturing facility, seen from above
Image: BWX Technologies (BWXT)
BWX Technologies · November 12, 2026 · Read the original → · Also reported by World Nuclear News

The US Nuclear Regulatory Commission has issued the construction permit for Long Mott Generating Station, the four-unit Xe-100 plant proposed for Dow's Seadrift site in Texas — the first NRC construction permit for a high-temperature gas-cooled reactor in nearly 60 years, and the first for a nuclear plant at an industrial site. The permit lets the project be built but not operated, and Dow still has to make its own investment decisions, with a preliminary decision expected in 2027, before full-scale construction begins. This follows the final safety review covered in Edition 1.

Aerial rendering of the Long Mott Generating Station, the four-unit Xe-100 plant planned for Dow's Seadrift site in Texas
A rendering of the Long Mott Generating Station. Image: X-energy
World Nuclear News · November 10, 2026 · Read the original → · X-energy's announcement, November 9, 2026

Oklo has turned its June letter of intent with Centrus Energy into definitive multi-year contracts for high-assay low-enriched uranium, enough to fuel up to five Aurora powerhouses for multiple years, with deliveries from Centrus' Piketon, Ohio plant scheduled to begin in 2029. Oklo's prepayments, backed by Meta's prepayment for future power, will help Centrus build new US enrichment capacity, and the fuel covers the first phase of Oklo's planned 1.2 GW Ohio campus.

Centrus' American Centrifuge Plant in Piketon, Ohio, seen from above
Centrus' American Centrifuge Plant in Piketon, Ohio. Image: Centrus Energy
Centrus Energy / Oklo · November 12, 2026 · Read the original →

The New York Power Authority has qualified 10 developers for potential partnership on at least 1 GW of advanced nuclear capacity in upstate New York. Six firms qualified for both large reactors and SMRs, while four advanced on the SMR path only: Blue Energy, Holtec International, TerraPower and X-energy — three of them companies tracked in the NuclearVox directory. A host community, technology and development partner are still to be chosen.

New York Power Authority · November 12, 2026 · Read the original →
Top-down rendering of Applied Atomics' SMR site design Image: Applied Atomics Inc.
Industry

Wisconsin co-op Dairyland to study SMRs at its Genoa site

Wisconsin's Dairyland Power Cooperative has signed a letter of intent with Applied Atomics to evaluate deploying that company's 100–150 MW SMRs at Dairyland's Genoa site, a former nuclear plant site that still holds a licensed spent fuel store, with a possible power purchase agreement to follow. A feasibility study comes first, and Dairyland says it expects to be able to decide on a binding PPA in roughly nine months, only if the numbers work for its members.

Top-down rendering of Applied Atomics' small modular reactor design
A rendering of Applied Atomics' SMR technology. Image: Applied Atomics Inc.
America's Electric Cooperatives (NRECA) · November 13, 2026 · Read the original →